Construction Status

Construction Status as on 31st Dec 2015

Tower No Status
A 18th floor concreting completed partially
B Above terrace work in progress
C RCC work completed
Staircase flooring & railing work in progress
Toilet wall tile work in progress
D Rcc work completed
Toilet wall tile work in progress
Elevator installation work in progress
E RCC works completed
Wall plastering in progress
Elevator installation work in progress
F 20th floor reinforcement & shuttering in progress
G 12th floor concreting completed
H 22nd floor reinforcement & shuttering in progress
J 15th floor concreting completed
Other Works Boundary wall in progress

  • SITE-B1B-TOWER-A-18TH-FLOOR-CONCRETING-COMPLETED-PARTIALLYSITE-B1B-TOWER-A-18TH-FLOOR-CONCRETING-COMPLETED-PARTIALLY
  • SITE-B1B-TOWER-B–ABOVE-TERRACE-WORK-IN-PROGRESSSITE-B1B-TOWER-B–ABOVE-TERRACE-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-C–RCC-WORK-COMPLETEDSITE-B1B-TOWER-C–RCC-WORK-COMPLETED
  • SITE-B1B-TOWER-C–STAIRCASE-FLOORING&RAILING-WORK-IN-PROGRESSSITE-B1B-TOWER-C–STAIRCASE-FLOORING&RAILING-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-C–TOILET-WALL-TILE-WORK-IN-PROGRESSSITE-B1B-TOWER-C–TOILET-WALL-TILE-WORK-IN-PROGRESS
  • SITE-B1A-TOWER-D–RCC-WORK-COMPLETEDSITE-B1A-TOWER-D–RCC-WORK-COMPLETED
  • SITE-B1A-TOWER-D–TOILET-WALL-TILE-WORK-IN-PROGRESSSITE-B1A-TOWER-D–TOILET-WALL-TILE-WORK-IN-PROGRESS
  • SITE-B1A-TOWER-D–ELEVATOR-INSTALLATION-WORK-IN-PROGRESSSITE-B1A-TOWER-D–ELEVATOR-INSTALLATION-WORK-IN-PROGRESS
  • SITE-B1A-TOWER-E–RCC-WORK-COMPLETEDSITE-B1A-TOWER-E–RCC-WORK-COMPLETED
  • SITE-B1A-TOWER-E–WALL-PLASTERING-IN-PROGRESSSITE-B1A-TOWER-E–WALL-PLASTERING-IN-PROGRESS
  • SITE-B1A-TOWER-E–ELEVATOR-INSTALLATION-WORK-IN-PROGRESSSITE-B1A-TOWER-E–ELEVATOR-INSTALLATION-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-F–20TH-FLOOR-REINFORCEMENT&SHUTTERING-IN-PROGRESSSITE-B1B-TOWER-F–20TH-FLOOR-REINFORCEMENT&SHUTTERING-IN-PROGRESS
  • SITE B2A-TOWER-G–12TH-FLOOR-CONCRETING-COMPLETEDSITE B2A-TOWER-G–12TH-FLOOR-CONCRETING-COMPLETED
  • SITEB2B-TOWER-H–22ND-FLOOR-REINFORCEMENT&SHUTTERING-IN-PROGRESSSITEB2B-TOWER-H–22ND-FLOOR-REINFORCEMENT&SHUTTERING-IN-PROGRESS
  • SITE B2B-TOWER-J–15TH-FLOOR-CONCRETING-COMPLETEDSITE B2B-TOWER-J–15TH-FLOOR-CONCRETING-COMPLETED
  • SITE-B1A–BOUNDARY-WALL-IN-PROGRESSSITE-B1A–BOUNDARY-WALL-IN-PROGRESS