Construction Status Archives

Construction Status as on 30th Nov 2015

Tower No Status
A 17th floor reinforcement in progress
Blockwork, electrical & firefighting work in progress
B Terrace slab completed
C RCC work completed
Ceiling & wall plastering in progress
Floor tile work in progress
Staircase stone flooring in progress
D RCC works completed
Floor tile work in progress
Ceiling & wall plaster work in progress
Toilet wall tile work in progress
Staircase stone flooring & railing work in progress
E RCC works completed
Ceiling & wall plastering in progress
F 18th floor reinforcement & shuttering in progress
Ceiling & wall plastering work in progress
Toilet wall tile work in progress
G 12th floor concreting completed partially
H 21st floor reinforcement & shuttering in progress
J 13th floor reinforcement & shuttering in progress
Other Club x1 – reinforcement work for 2nd floor in progress
Other OVERALL development

  • SITE-B1A-TOWER-D-FLOOR-TILE-WORK-IN-PROGRESSSITE-B1A-TOWER-D-FLOOR-TILE-WORK-IN-PROGRESS
  • SITE-B1A-TOWER-E-CEILING-&-WALL-PLASTERING-IN-PROGRESSSITE-B1A-TOWER-E-CEILING-&-WALL-PLASTERING-IN-PROGRESS
  • SITE-B1A-TOWER-D-RCC-WORK-COMPLETEDSITE-B1A-TOWER-D-RCC-WORK-COMPLETED
  • SITE-B1A-TOWER-D-TOILET-WALL-TILE-WORK-IN-PROGRESSSITE-B1A-TOWER-D-TOILET-WALL-TILE-WORK-IN-PROGRESS
  • SITE-B1A-TOWER-D-STAIRCASE-STONE-FLOORING-&-RAILING-WORK-IN-PROGRESSSITE-B1A-TOWER-D-STAIRCASE-STONE-FLOORING-&-RAILING-WORK-IN-PROGRESS
  • OVERALL-VIEW-OF-SITE-B1AOVERALL-VIEW-OF-SITE-B1A
  • SITE-B1A-TOWER-E-RCC-WORK-COMPLETEDSITE-B1A-TOWER-E-RCC-WORK-COMPLETED
  • SITE-B1A-TOWER-D-CEILING-&-WALL-PALSTER-WORK-IN-PROGRESSSITE-B1A-TOWER-D-CEILING-&-WALL-PALSTER-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-B-TERRACE-SLAB-COMPLETEDSITE-B1B-TOWER-B-TERRACE-SLAB-COMPLETED
  • SITE-B1B-OVERALL-VIEW-OF-SITE-B1BSITE-B1B-OVERALL-VIEW-OF-SITE-B1B
  • SITE-B1B-TOWER-A-BLOCKWORK-ELECTRICAL-&-FIREFIGHTING-WORK-IN-PROGRESSSITE-B1B-TOWER-A-BLOCKWORK-ELECTRICAL-&-FIREFIGHTING-WORK-IN-PROGRESS
  • SITE-B1B-CLUB-X1-REINFORCEMENT-WORK-FOR-2ND-FLOOR-IN-PROGRESSSITE-B1B-CLUB-X1-REINFORCEMENT-WORK-FOR-2ND-FLOOR-IN-PROGRESS
  • SITE-B1B-TOWER-C-RCC-WORK-COMPLETEDSITE-B1B-TOWER-C-RCC-WORK-COMPLETED
  • SITE-B1B-TOWER-F-TOILET-WALL-TILE-WORK-IN-PROGRESSSITE-B1B-TOWER-F-TOILET-WALL-TILE-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-F-CEILING-&-WALL-PLASTERING-WORK-IN-PROGRESSSITE-B1B-TOWER-F-CEILING-&-WALL-PLASTERING-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-C-STAIRCASE-STONE-FLOORING-IN-PROGRESSSITE-B1B-TOWER-C-STAIRCASE-STONE-FLOORING-IN-PROGRESS
  • SITE-B1B-TOWER-C-FLOOR-TILE-WORK-IN-PROGRESSSITE-B1B-TOWER-C-FLOOR-TILE-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-C-CEILING-&-WALL-PALSTERING-IN-PROGRESSSITE-B1B-TOWER-C-CEILING-&-WALL-PALSTERING-IN-PROGRESS
  • SITE-B1B-TOWER-F-18TH-FLOOR-REINFORCEMENT-&-SHUTTERING-IN-PROGRESSSITE-B1B-TOWER-F-18TH-FLOOR-REINFORCEMENT-&-SHUTTERING-IN-PROGRESS
  • SITE-B1B-TOWER-A-17TH-FLOOR-REINFORCEMENT-IN-PROGRESSSITE-B1B-TOWER-A-17TH-FLOOR-REINFORCEMENT-IN-PROGRESS
  • SITE-B2B-TOWER-J-13TH-FLOOR-REINFORCEMENT-&-SHUTTERING-IN-PROGRESSSITE-B2B-TOWER-J-13TH-FLOOR-REINFORCEMENT-&-SHUTTERING-IN-PROGRESS
  • SITE-B2B-TOWER-H-21ST-FLOOR-REINFORCEMENT-&-SHUTTERING-IN-PROGRESSSITE-B2B-TOWER-H-21ST-FLOOR-REINFORCEMENT-&-SHUTTERING-IN-PROGRESS
  • SITE-B2A-TOWER-G-12TH-FLOOR-CONCRETING-COMPLETED-PARTIALLYSITE-B2A-TOWER-G-12TH-FLOOR-CONCRETING-COMPLETED-PARTIALLY