Construction Status

Construction Status as on 30th Jan 2016

Tower No Status
A 19th floor concreting completed partially
Floor tile work in progress
Toilet wall tile work in progress
B Above terrace work in progress
C Rcc work completed
Kitchen wall tile work in progress
Toilet wall tile work in progress
D Rcc work completed
Toilet wall tile work in progress
Kitchen wall tile work in progress
Elevator installation work in progress
E Rcc work completed
Kitchen wall tile work in progress
Toilet wall tile work in progress
Elevator installation work in progress
F 21st floor reinforcement & shuttering in progress
Toilet wall tile work in progress
G 12th floor concreting completed
H 23rd floor reinforcement & shuttering in progress
J 17th floor concreting completed partially
Other Shopping – block work in progress
Boundary wall in progress
Club x1 – above terrace work in progress

  • SITE-B1A-TOWER-D-ELEVATOR-INSTALLATION-WORK-IN-PROGRESSSITE-B1A-TOWER-D-ELEVATOR-INSTALLATION-WORK-IN-PROGRESS
  • SITE-B1A-TOWER-E-RCC-WORK-COMPLETEDSITE-B1A-TOWER-E-RCC-WORK-COMPLETED
  • SITE-B1A-TOWER-D-TOILET-WALL-TILE-WORK-IN-PROGRESSSITE-B1A-TOWER-D-TOILET-WALL-TILE-WORK-IN-PROGRESS
  • SITE-B1A-TOWER-D-RCC-WORK-COMPLETEDSITE-B1A-TOWER-D-RCC-WORK-COMPLETED
  • SITE-B1A-TOWER-E-KITCHEN-WALL-TILE-WORK-IN-PROGRESSSITE-B1A-TOWER-E-KITCHEN-WALL-TILE-WORK-IN-PROGRESS
  • SITE-B1B-CLUB-X1-ABOVE-TERRACE-WORK-IN-PROGRESSSITE-B1B-CLUB-X1-ABOVE-TERRACE-WORK-IN-PROGRESS
  • SITE-B1A-TOWER-E-ELEVATOR-INSTALLATION-WORK-IN-PROGRESSSITE-B1A-TOWER-E-ELEVATOR-INSTALLATION-WORK-IN-PROGRESS
  • SITE-B1A-TOWER-E-TOILET-WALL-TILE-WORK-IN-PROGRESSSITE-B1A-TOWER-E-TOILET-WALL-TILE-WORK-IN-PROGRESS
  • SITE-B1A-TOWER-D-KITCHEN-WALL-TILE-WORK-IN-PROGRESSSITE-B1A-TOWER-D-KITCHEN-WALL-TILE-WORK-IN-PROGRESS
  • SITE-B1B-BOUNDARY-WALL-IN-PROGRESSSITE-B1B-BOUNDARY-WALL-IN-PROGRESS
  • SITE-B1B-TOWER-A-TOILET-WALL-TILE-WORK-IN-PROGRESSSITE-B1B-TOWER-A-TOILET-WALL-TILE-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-A-19TH-FLOOR-CONCRETING-COMPLETED-PARTIALLYSITE-B1B-TOWER-A-19TH-FLOOR-CONCRETING-COMPLETED-PARTIALLY
  • SITE-B1B-TOWER-A-FLOOR-TILE-WORK-IN-PROGRESSSITE-B1B-TOWER-A-FLOOR-TILE-WORK-IN-PROGRESS
  • SITE-B2B-TOWER-J-17TH-FLOOR-CONCRETING-COMPLETED-PARTIALLYSITE-B2B-TOWER-J-17TH-FLOOR-CONCRETING-COMPLETED-PARTIALLY
  • SITE-B2A-SHOPPING-BLOCK-WORK-IN-PROGRESSSITE-B2A-SHOPPING-BLOCK-WORK-IN-PROGRESS
  • SITE-B2B-TOWER-G-12TH-FLOOR-CONCRETING-COMPLETEDSITE-B2B-TOWER-G-12TH-FLOOR-CONCRETING-COMPLETED
  • SITE-B1B-TOWER-C-RCC-WORK-COMPLETEDSITE-B1B-TOWER-C-RCC-WORK-COMPLETED
  • SITE-B1B-TOWER-B-ABOVE-TERRACE-WORK-IN-PROGRESSSITE-B1B-TOWER-B-ABOVE-TERRACE-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-C-KITCHEN-WALL-TILE-WORK-IN-PROGRESSSITE-B1B-TOWER-C-KITCHEN-WALL-TILE-WORK-IN-PROGRESS
  • SITE-B2B-TOWER-H-23RD-FLOOR-REINFORCEMENT-&-SHUTTERING-IN-PROGRESSSITE-B2B-TOWER-H-23RD-FLOOR-REINFORCEMENT-&-SHUTTERING-IN-PROGRESS
  • SITE-B1B-TOWER-F-21-ST-FLOOR-REINFORCEMENT-&-SHUTTERING-IN-PROGRESSSITE-B1B-TOWER-F-21-ST-FLOOR-REINFORCEMENT-&-SHUTTERING-IN-PROGRESS
  • SITE-B1B-TOWER-F-TOILET-WALL-TILE-WORK-IN-PROGRESSSITE-B1B-TOWER-F-TOILET-WALL-TILE-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-C-TOILET-WALL-TILE-WORK-IN-PROGRESSSITE-B1B-TOWER-C-TOILET-WALL-TILE-WORK-IN-PROGRESS