Construction Status as on 15th Jan 2016

Construction Status as on 15th Jan 2016

Tower No Status
A 18th floor concreting completed
Wall plaster in progress
B Above terrace work in progress
Block work & electrical work in progress
C Rcc work completed
Ceiling & wall plaster in progress
D Rcc work completed
Ceiling & wall plaster in progress
Staircase flooring & railing work in progress
E Rcc work completed
Ceiling & wall plaster in progress
F 20th floor concreting completed partially
G 12th floor concreting completed
H 23rd floor reinforcement & shuttering in progress
Block work & electrical work in progress
J 16th floor concreting completed partially
Club Above terrace work in progress
Other Overall view of site

  • SITE-B1B-OVERALL-VIEW-OF-SITE-B1BSITE-B1B-OVERALL-VIEW-OF-SITE-B1B
  • SITE-B1A-TOWER-E-RCC-WORK-COMPLETEDSITE-B1A-TOWER-E-RCC-WORK-COMPLETED
  • SITE-B1A-TOWER-D-RCC-WORK-COMPLETEDSITE-B1A-TOWER-D-RCC-WORK-COMPLETED
  • SITE-B1B-CLUB-X1-ABOVE-TERRACE-WORK-IN-PROGRESSSITE-B1B-CLUB-X1-ABOVE-TERRACE-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-B-BLOCKWORK-&-ELECTRICAL-WORK-IN-PROGRESSSITE-B1B-TOWER-B-BLOCKWORK-&-ELECTRICAL-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-A-18TH-FLOOR-CONCRETING-COMPLETEDSITE-B1B-TOWER-A-18TH-FLOOR-CONCRETING-COMPLETED
  • SITE-B1B-TOWER-A-WALL-PLASTER-IN-PROGRESSSITE-B1B-TOWER-A-WALL-PLASTER-IN-PROGRESS
  • OVERALL-VIEW-OF-SITE-B1AOVERALL-VIEW-OF-SITE-B1A
  • SITE-B1A-TOWER-E-CEILING-&-WALL-PLASTER-IN-PROGRESSSITE-B1A-TOWER-E-CEILING-&-WALL-PLASTER-IN-PROGRESS
  • SITE-B1B-TOWER-B-ABOVE-TERRACE-WORK-IN-PROGRESSSITE-B1B-TOWER-B-ABOVE-TERRACE-WORK-IN-PROGRESS
  • SITE-B1A-TOWER-D-CEILING-&-WALL-PLASTER-IN-PROGRESSSITE-B1A-TOWER-D-CEILING-&-WALL-PLASTER-IN-PROGRESS
  • SITE-B1A-TOWER-D-STAIRCASE-FLOORING-&-RAILING-WORK-IN-PROGRESSSITE-B1A-TOWER-D-STAIRCASE-FLOORING-&-RAILING-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-C-CEILING-&-WALL-PLASTER-IN-PROGRESSSITE-B1B-TOWER-C-CEILING-&-WALL-PLASTER-IN-PROGRESS
  • SITE-B2A-TOWER-G-12TH-FLOOR-CONCRETING-COMPLETEDSITE-B2A-TOWER-G-12TH-FLOOR-CONCRETING-COMPLETED
  • SITE-B1B-TOWER-F-20TH-FLOOR-CONCRETING-COMPLETED-PARTIALLYSITE-B1B-TOWER-F-20TH-FLOOR-CONCRETING-COMPLETED-PARTIALLY
  • SITE-B2B-TOWER-H-23RD-FLOOR-REINFORCEMENT-&-SHUTTERING-IN-PROGRESSSITE-B2B-TOWER-H-23RD-FLOOR-REINFORCEMENT-&-SHUTTERING-IN-PROGRESS
  • SITE-B2B-TOWER-J-16TH-FLOOR-CONCRETING-COMPLETED-PARTIALLYSITE-B2B-TOWER-J-16TH-FLOOR-CONCRETING-COMPLETED-PARTIALLY
  • SITE-B1B-TOWER-C-RCC-WORK-COMPLETEDSITE-B1B-TOWER-C-RCC-WORK-COMPLETED
  • SITE-B2B-TOWER-H-BLOCKWORK-&-ELECTRICAL-WORK-IN-PROGRESSSITE-B2B-TOWER-H-BLOCKWORK-&-ELECTRICAL-WORK-IN-PROGRESS