Construction Status as on 15th Feb 2016

Tower No Status
A 21st floor reinforcement & shuttering in progress
Ceiling & wall plaster in progress
B Above terrace work in progress
Blockwork, electrical & firefighting work in progress
C Rcc work completed
Ceiling & wall plaster in progress
D Rcc work completed
Ceiling & wall plaster in progress
E Rcc work completed
Ceiling & wall plaster in progress
F 21st floor reinforcement & shuttering in progress
Ceiling plaster in progress
G 12th floor concreting completed
H 23rd floor reinforcement & shuttering in progress
J 18th floor concreting completed partially
Club Club x1 – above terrace work in progress
Other Overall view of site B1B
Boundary wall in progress
Upper basement services work in progress

  • SITE-B1A-TOWER-D-CEILING&WALL-PLASTER-IN-PROGRESSSITE-B1A-TOWER-D-CEILING&WALL-PLASTER-IN-PROGRESS
  • SITE-B1A-TOWER-D-RCC-WORK-COMPLETEDSITE-B1A-TOWER-D-RCC-WORK-COMPLETED
  • SITE-B1B-CLUB-X1-ABOVE-TERRACE-WORK-IN-PROGRESSSITE-B1B-CLUB-X1-ABOVE-TERRACE-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-B-BLOCKWORK,ELECTRICAL&FIREFIGHTING-WORK-IN-PROGRESSSITE-B1B-TOWER-B-BLOCKWORK,ELECTRICAL&FIREFIGHTING-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-A-CEILING&WALL-PLASTER-IN-PROGRESSSITE-B1B-TOWER-A-CEILING&WALL-PLASTER-IN-PROGRESS
  • SITE-B1B-TOWER-A-21ST-FLOOR-REINFORCEMENT&SHUTTERING-IN-PROGRESSSITE-B1B-TOWER-A-21ST-FLOOR-REINFORCEMENT&SHUTTERING-IN-PROGRESS
  • SITE-B1B-TOWER-C-CEILING&WALL-PLASTER-IN-PROGRESSSITE-B1B-TOWER-C-CEILING&WALL-PLASTER-IN-PROGRESS
  • SITE-B1A-TOWER-E-RCC-WORK-COMPLETEDSITE-B1A-TOWER-E-RCC-WORK-COMPLETED
  • SITE-B1B-OVERALL-VIEW-OF-SITE-B1BSITE-B1B-OVERALL-VIEW-OF-SITE-B1B
  • SITE-B1B-BOUNDARY-WALL-IN-PROGRESSSITE-B1B-BOUNDARY-WALL-IN-PROGRESS
  • SITE-B1A-TOWER-E-CEILING-&-WALL-PLASTER-IN-PROGRESSSITE-B1A-TOWER-E-CEILING-&-WALL-PLASTER-IN-PROGRESS
  • SITE-B1B-TOWER-B-ABOVE-TERRACE-WORK-IN-PROGRESSSITE-B1B-TOWER-B-ABOVE-TERRACE-WORK-IN-PROGRESS
  • SITE-B1B-TOWER-C-RCC-WORK-COMPLETEDSITE-B1B-TOWER-C-RCC-WORK-COMPLETED
  • SITE-B2B-TOWER-H-23RD-FLOOR-REINFORCEMENT&SHUTTERING-IN-PROGRESSSITE-B2B-TOWER-H-23RD-FLOOR-REINFORCEMENT&SHUTTERING-IN-PROGRESS
  • SITE-B1B-UPPER-BASEMENT-SERVICES-WORK-IN-PROGRESSSITE-B1B-UPPER-BASEMENT-SERVICES-WORK-IN-PROGRESS
  • SITE-B2A-12TH-FLOOR-CONCRETING-COMPLETEDSITE-B2A-12TH-FLOOR-CONCRETING-COMPLETED
  • SITE-B1B-TOWER-F-CEILING-PLASTER-IN-PROGRESSSITE-B1B-TOWER-F-CEILING-PLASTER-IN-PROGRESS
  • SITE-B1B-TOWER-F-21ST-FLOOR-REINFORCEMENT&SHUTTERING-IN-PROGRESSSITE-B1B-TOWER-F-21ST-FLOOR-REINFORCEMENT&SHUTTERING-IN-PROGRESS
  • SITE-B2B-TOWER-J-18TH-FLOOR-CONCRETING-COMPLETED-PARTIALLYSITE-B2B-TOWER-J-18TH-FLOOR-CONCRETING-COMPLETED-PARTIALLY